Print version

It is invested by Quang Ngai Mineral Investment JSC - a member of NBB. It is located in Tinh Hiep Village, Son Ninh Ward, Quang Ngai Provinces. The project area is 25ha. The expected completion time will be 18 years. Exploitation capacity is 100,000m3/year. NBB finances 90%. This project is now receiving the exploration result and preparing the base design and investment plan. 

---

Scale:

- Gross area:

25 ha

- Exploitation capactity:

100,000 m3/year

- Exploitation time:

18 years

- Total investment capital:

25bn VND


Progress:

- The report exploration result was approved under Decision No. 1630/QD-UBND dated 19th September 2010 by People’s Committee of Quang Ngai Province.
- Ongoing to implement procedure relating to basic design.

- The investment project has submitted to be approved.

---