Located on the main road of Vo Van Kiet (extended), Tan Nhut commune, Ho Chi Minh City, the project covers an area of 7.88 hectares; with a land use ratio of 3.0 times; a total floor area of 171,931.35 m2 for apartment and commercial buildings, equivalent to 1,500 apartments in two separate blocks with a maximum height of 18 floors, apartment sizes ranging from 68-84 m2, along with many amenities such as a kindergarten, a secondary school for the area, a swimming pool, a gym, a modern park, etc. The project has a total investment of VND 2,000 billion, of which 577 is 100% invested.
-
Scale
-
Land area for apartment and commercial construction 31.519,91 m2
- Land area for apartment building in Zone A 10.448,62 m2
- Total number of apartments in Zone A 610 apartments
- Land area for apartment building in Zone B 21.071,29 m2
- Total number of apartments in Block B 890 apartments
- Total number of commercial units 45 units
-
Land area for building the kindergarten: 1.916,20 m2
- Total floor area of the kindergarten building 1.916,20 m2
- Projected building density 36,8 %
- 16 Expected floor height 2 floors
-
Land area for constructing a secondary school in the area. 8.748,57 m2
- Total floor area 13.997,68 m2
- Projected building density 40 %
- Expected number of floors: 4 floors
-
Total investment: 2,000 billion VND
-
-
Project progress
- The project has completed compensation for 100% of the land area.
- The project has received approval in principle from the Ho Chi Minh City People's Committee for investment and the investor has been approved in Decision 3108/QD-UBND dated June 21, 2025.
- Currently, the investor is collaborating with a consulting firm to prepare the 1/500 scale detailed planning.